The last few weeks have been rather productive on the CSX Chickamauga. Bought two
locomotives with my tax return, an Atlas Family Lines MP-15 and Atlas
Family Lines U30C, with a third unit on the way, an Atlas Seaboard
System B30-7. Also bought materials to do another batch of Supertrees
and have started the boiling and drying process on them last week.
Completed scratchbuilding the abutments for the TVRM girder bridge,
which to date has been probably the most complex portion of this layout
project. Picture if you will: a former double-track mainline on a long
fill that slices across the layout at roughly a 30 degree angle to the
fascia, crossing the CSX main, which itself is travelling at about a 4
degree angle to the fascia. Okay, now add to that a six-segment skewed
girder bridge that will be suspended across the CSX main by two
scratchbuilt styrene abutments and six plaster (simulated concrete)
pilings. Consider that the whole mess occupies about five linear feet of
my 10' x 15' layout, will be the most eyecatching and distinctive
feature, and is so complex that it required plotting out not only in
AutoCAD but also in realtime using 24" wide banner paper as a mockup,
and you will understand what I'm up against with this project. I have
the abutments fully fabbed, and have sanded and primered out the
defects; next comes painting and weathering them, followed by
installation and scenery work on the fill.
Also completed painting and installation of my auger loader, a piece
of machinery engineered to dispense conical piles of ballast into
waiting cars at the Vulcan Materials facility as modeled on the layout.
Essentially comprised of PVC pipe, a funnel, an auger bit, an
automotive wiper motor, and various assorted bits of hardware, this
device also required plotting out in AutoCAD in order to obtain maximum
design efficiency. I am really pleased with the result of this project,
as it adds increased challenge and enjoyment to my operating sessions.
Furthermore, I have completed the painting and installation of my car
card boxes on each CTC panel, making operation more efficient and
enjoyable. Also managed to get an initial coat of weathering on 15 more
freight cars, including painting the trucks, which first had to be
soda-blasted for better paint adhesion.
Last night I added railings to the Shallowford Road overpasses, kitbashed with styrene and Rix Products Wrought Iron Overpass Railings. I am pleased with the way this project turned out, much better than I anticipated. The next step is airbrushing them an aged concrete color, followed by weathering and installation in their respective positions on the layout.
The next big hurdle is procuring the necessary items for the crossing
installation at Lightfoot Mill Road, near Tyner Junction. I figure
this will run me about 100 dollars; I will need another Grade Crossing
Pro circuit from Logic Rail Technologies and a bell ringer circuit from
ITT, plus a pair of signals from NJ International and additional
photocells to activate the circuit, considering it is a two-track
crossing.
Another big item on the to-do list is to complete the shop/office
complex and loading dock of Sequatchie Concrete Services, and the cement
unloading bins at Sherman Dixie Products Co.
So many projects, so little time...
Monday, March 26, 2012
Prototype research in the 21st Century, A.K.A. "The Internet rocks!"
In this post-9/11 world, it can be difficult for a modeler
to obtain the information he needs through good, old-fashioned research, such as
visiting the site and shooting pics.
Many of the industries served by rail receive shipments of dangerous
chemicals and thus are not too friendly to the public; arguably for good
reason. I no longer railfan anymore, haven’t since 2005, when I was hassled by
the police. So in many cases I’ve had to adapt my research habits.
Enter Google Streetview.
Recently I was filling out car cards and waybills for the
CSX Chickamauga. I use the four-sided waybills touted by David Barrow, Tony
Koester, and others ( I’m thinking of converting to switch lists but that is
another story for another blog for another day…). It occurred to me that I didn’t
know what the BASF plant on Polymer Drive in Chattanooga receives by rail, and
I wanted this information to complete an accurate waybill. I could’ve rocked on
without it just the same, but I figured it was worth a shot to try and find
out. The BASF plant is represented on my layout by a staging track; I knew from my
field research that this plant produces products for the carpet industry, since
I have seen Shaw Flooring trucks backed up to the loading docks there while
driving by. Luckily the house track that CSX uses to store cars for BASF
closely parallels Airport Road, and a quick stroll in Google Streetview revealed
the tank car numbers. The images are not clear enough to obtain the UN numbers
from the placards, however. No big deal, I’ll just cruise on over to http://www.rrpicturearchives.net
and see if I can read them there. Sure enough, I found the exact cars and was
able to read their placard numbers; UN 2055 and UN 1010, which is Styrene (Monomer)
and Butadiene, respectively. According to Wikipedia, both chemicals are
commonly used in the manufacturing of carpet backing. BINGO! I had my answer. Google searches on the BASF
operations in Chattanooga more or less confirmed my findings.
So, in short, with the Internet I was able to find out
information that I would likely otherwise not be able obtain, a least not without
possibly jeopardizing my blemish-free criminal record, or at the very least
having to explain myself to some puzzled police officer. As a bonus, I learned
a bit about the manufacturing process of carpet. At the very least, it made for
a very interesting Sunday afternoon.
I have referenced Bing Maps and Streetview many other times
during the construction of the CSX Chickamauga, obtaining measurements for
everything from location of street markings to observing the location of trees
and street signs, to plotting the ridgeline of my backdrop, and even observing
the shape and estimating the dimensions of bridge railings. All without leaving the comfort of my home. These services are
truly indispensible and should be prominently located in the research arsenal
of any modern modeler.
Isn’t the Internet awesome? :-)
Photos of the CSX Chickamauga as of March 2012
The engineer on CSXT 5560
has 'er skinned back to 40 MPH and is laying down on the horn for Cromwell Road
as train 122, a hotshot pig/container train bound for Chicago, clatters through
the switches at Chickamauga, TN.
Seaboard
System #4214 is crossing Lightfoot Mill Road, making its way southbound
in May 1985 with a short local----an empty boxcar for loading at
Sequatchie Concrete Services and a car of portland cement for
Sherman-Dixie Products Co. Looks like a storm front is blowing in.
Blast
from the Past.... We step back to April 1979, as we watch L&N 2746
swing off of the Tyner branch, headed back to Wauhatchie Yard with the
day's loads from the Volunteer Army Ammunition Plant at Tyner.
Adventures in choosing a prototype locale
Having formally arrived, in the Spring of 2011, at the
decision to model the Chickamauga Creek area of Chattanooga, Tennessee along the CSX
Atlanta-to-Nashville main line, I can say, in retrospect, it was NOT an easy
decision. In fact, it was a bit of a journey to this destination; a complicated
means to a fitting end, if you will.
The journey began in mid-2007, when I began construction of
the modules that serve as the framework for the CSX Chickamauga. At that time I
had been amassing a collection of HO scale equipment after re-entry to the
hobby from a brief hiatus, ending in Summer of 2004. Due to my employment during
that era, I was able to build quite a roster of the latest offerings from
Atlas, Athearn, Intermountain, and Walthers; roughly 300 cars and some 40 locomotives.
I knew from the beginning I would want to model early CSX, since that’s what I
grew up railfanning, and therefore holds sentimentality for me. So roadname and
era was not an issue, fortunately. I quickly
began buying up any models that caught my eye and could be found on CSX in the mid
1980’s to early 1990’s. I also bought quite a few models appropriate for early
Norfolk Southern, with the intent of someday modeling interchange traffic.
Having all this nice equipment, with no place to run and
enjoy it, was quite frustrating. Around mid-2007, I began investigating whether or not I
could shoehorn a layout into my office/den. A 13 x 15 foot room containing at least one window or door on each wall, a small
corner closet, and not to mention my desk, entertainment center, and bookcase,
would yield a decent 10 x 15 foot space for a switching layout, provided I
built it high enough to clear the top of my bookcase. Not a problem, since I
tend to like high layout benchwork anyway. But the question was, could I live with only a point-to-point layout with no continuous run? Shortly after
completing the rough carpentry on the modules, I decided I couldn’t. Furthermore,
dust abatement was/is an issue in my 1907 restored home with central HVAC.
These two issues led to over a year of stalling on the project.
Fast forward to September 2008, when I finally got
frustrated enough with not being able to run my trains that I decided to bite
the bullet and live with not having a continuous run. As for the household dust
problem, it occurred to me that I could build a modular shadowbox to fit over
the modules. This would kill several birds with one stone; it would (1) keep
dust off of the scenery, (2) provide a great framework for good lighting (the
room lighting in my office is rather anemic), (3) double as a shelf to store
all of my locomotives and rolling stock and their respective packaging when not
in use, and (4) serve as a visual “picture frame” for the layout, drawing
visitors’ eyes into the scene. So I jumped back into the project full speed
ahead and by January 2009 I had the three modules installed in my office. It
was then that I stumbled headlong into a big problem.
“Uhmm, ok. Now what area
do I model?”
All of my past layouts had always used freelanced, “imaginary”
settings somewhere in the southeastern United States. I knew that this time around, with all my
prototypical equipment that I had invested much money and effort into closely
modeling early CSX, that I wanted to be equally prototypical with modeling a
real-life setting. And there is where the madness began…
Initially, since a considerable part of my fleet is
comprised of cars that would serve paper traffic--pulpwood cars, woodchip cars,
tank cars, 50 and 60 foot boxcars, etc.-- I decided to model the local Bowater
Southern paper mill in Charleston, Tennessee. I’ve always had a fascination
with the rail activity surrounding paper mills, and this one was no exception,
being served by both CSX and NS. But a funny thing happened right around the
time I moved the finished modules into my office….I encountered a big shakeup
in my professional life, which led to a laborer job at that exact paper mill.
My experience there quickly soured me on the thoughts of ever modeling it. (Would
YOU want to model the place YOU work at? I didn’t think so….) So, back to square one in terms of modeling a
specific locale.
I have always wanted to model the “New Line”, i.e. the CSX
main from Atlanta to Cincinnati by way of Knoxville, Tennessee and Etowah, Tennessee. I even
got so far as drafting up a GREAT track plan representing downtown Knoxville in
XtrkCAD. But, two big problems with that line: (1) sparse online industry, a
big negative since I enjoy running local trains and switching cars the most,
and (2) it hosts an endless parade of coal trains, mostly comprised of a car
that nobody currently makes in HO scale, the Trinity RD-2 hopper. I knew from
experience (my previous layout was set in a fictional West Virginia locale)
that coal trains can quickly get boring, and I wanted to do something
different. So, strike off the “New Line”, and with it, the downtown Knoxville
plan.
Groan. It was looking like I was going to have to freelance
again. Perish the thought. It was Spring 2009, and there I was, nearly 2 years
into a layout project and I still hadn’t even decided for certain what area to model. How
depressing. Right around this time I was experimenting with an idea I had
concerning animation; I wanted to build an operating auger loader to actually
deposit live loads into waiting hopper cars. Several dozen hours of testing and
experimentation proved that the idea was feasible, but given the operating
dynamics of the loader, it is not suited to loading long trains. Not a big
deal, since my layout is only 10 x 15 feet and thus couldn’t contain a long
25-30 car drag anyway. As if I needed
another reason, that ruled out modeling coal trains even further. Alright, so
what industry can I model that would make use of relatively short trains and a
working loader? Not coal, not woodchips…. Let’s see….I’ve got it… A QUARRY!
So there I was, with grand plans to build a working auger loader.
I quickly discovered that such an idea would basically require designing and
building the entire layout around the idea of the loader if I was going to be prototypical
about it.
Which naturally led to more stalling.
I spent the next year-and-a-half caught
between trying to find a quarry served by CSX and trying to accept the
possibility of freelancing my locale. (All was not lost, since I had temporary
track laid out on my modules during this time and ran trains frequently). I must’ve looked at every rail-served quarry
in the southeastern United States via Google Earth and Bing Maps. You see, I
had a rather lengthy list of “druthers”, as the late great John Armstrong would
say, as far as picking a location to model goes….It had to be a quarry located
on CSX trackage, preferably a mainline, preferably with rural scenery, and near
a Norfolk Southern interchange. I wanted to model at least one major road
crossing with signals, one significant waterway, and enough industry outside of
the quarry to make switching truly interesting and use a wider variety of my
rolling stock. Preferably not located too far from my home, so I could visit
and research it in person without needing to buy a plane ticket. Also it was
preferable that it be located in former L&N territory, since I have several
pieces of pre-CSX L&N rolling stock that I run occasionally. Last, but certainly not least, it had
to be easily adaptable to my modules, without excessive flipping or
compression.
First I looked at Kennesaw, Georgia:
Former L&N territory? Check.
Rail served quarry on CSX? Check.
Rural scenery? Sort of.
Various outside industry? Not really.
Nearby NS interchange? Nope.
Body of water? Negative.
Darn. Three negatives. On to the next one. Junction City,
Georgia; huge quarry out in the woods served by both CSX and NS, very
impressive, but its crossroads-style X-shape proved nearly impossible to adapt to my
L-shaped arrangement of modules. NEXT! Tate, Georgia: famous marble quarry. Former
L&N territory but no longer served by CSX after 1987. I’d have to stretch
plausibility quite a bit, plus the lay of the land (steep grades) would be
difficult to do on my modules. Try
again. Newnan, Georgia…served by NS only. Darn again. Same goes for Franklin
Industrial Minerals near Crab Orchard, Tennessee. It actually has its own
railroad connecting with NS.
I looked at quarries located in Georgia, Tennessee, North
Carolina, South Carolina, Virginia, Alabama, Florida, and Mississippi, only to dismiss
them one after one, for various reasons. Funny that I never ran across the one
I ended up modeling while doing my Bing Map/Google Earth travels. One reason
may be that it is rather small as quarries go, another reason is that it is no
longer rail served, actually I’m only about 80 percent sure it ever had rail
service. Oh well, it does on my layout anyway.
Fast forward to Fall 2010, when a trip to the Tennessee
Valley Railroad Museum revealed to me the nearby industrial park, smack-dab on
the CSX main, in former L&N territory, on the banks of Chickamauga Creek, with
numerous road crossings, several ancillary industries, and wouldn’t you know
it, it would drop right onto my modules with a spacious 4:1 compression ratio! And
the nearby branch line to Tyner, Tennessee once served as an interchange
between CSX and NS. And all located less than an hour’s drive from my home! Perfect! I quickly refined a track plan using AnyRail
software and had track laid out temporarily by the time Christmas 2010 rolled
around. I ultimately waited until Spring 2011 to commence with permanent track
installation, as I wanted to be absolutely sure that my track plan was
operationally satisfying before I cast it in stone (pun intended). It had been
three-and-a-half years, and dozens of hours of research and track planning, but
finally I felt comfortable with the prototype I had chosen.
So there you have it, I guess the moral of the story is: DON’T
GIVE UP WHEN SEARCHING FOR A PROTOTYPE LOCATION TO MODEL. If you search long
enough, you are bound to find something that is manageable without introducing
too many compromises on yourself.
Subscribe to:
Posts (Atom)